題目

What is the value of the closing work in progress on 30 November?

A

$2,440

B

$3,720

C

$4,104

D

$20,520

掃碼查看暗號,即可獲得解鎖答案!

點擊獲取答案
考點:Chapter11Processcosting

Using the data from answer 7 above, extend step 3 to calculate the value of the work in progress.

???? Cost???????????????? ?Number of??????????????? ?Cost per

???? element????????? ?equivalent units???????? ?equivalent unit??????????? Total

多做幾道

What was the actual usage of direct material during February?

A

800 kg

B

1,000 kg

C

1,200 kg

D

None of these

What was the selling price variance for February?

A

$120 (F)

B

$900 (A)

C

$1,200 (A)

D

$1,200 (F)

What was the sales volume profit variance for February?

A

$900 (F)

B

$1,200 (F)

C

$900 (A)

D

$2,100 (A)

材料全屏
30

【簡答題】

From the information provided calculate

(i)?The actual price paid per kg for the direct material?

(ii)?The standard quantity that should have been used for actual production.

Which of the following is likely to lead to the variances stated above?

A

lower quality direct material has been purchased

B

?higher quality direct material has been purchased