篩選結(jié)果 共找出525

Which of the following variances should a production manager be held responsible for??

A

?Material price planning variance?

B

?Material price operational variance?

C

?Material usage planning variance?

D

Material usage operational variance?

PG budgeted sales for 20X8 were 5,000 units. The standard contribution is $9.60 per unit. A recession in?20X8 meant that the market for PG's products declined by 5%. PG's market share also fell by 3%. Actual?sales were 4,500 units.?

Required?

Calculate planning and operational variances for sales volume.?

KSO budgeted to sell 10,000 units of a new product during 20X0. The budgeted sales price was $10 per?unit, and the variable cost $3 per unit.?Actual sales in 20X0 were 12,000 units and variable costs of sales were $30,000, but sales revenue was?only $5 per unit. With the benefit of hindsight, it is realised that the budgeted sales price of $10 was?hopelessly optimistic, and a price of $4.50 per unit would have been much more realistic.?

Required?

Calculate planning and operational variances for sales price.?

A company makes a single product. At the beginning of the budget year, the standard labour cost was?established as $8 per unit, and each unit should take 0.5 hours to make.??

However, during the year, the standard labour cost was revised. A new quality control procedure was?introduced to the production process, adding 20% to the expected time to complete a unit. In addition,?due to severe financial difficulties facing the company, the workforce reluctantly agreed to reduce the rate?of pay to $15 per hour.?

In the first month after revision of the standard cost, budgeted production was 15,000 units but only?14,000 units were actually produced. These took 8,700 hours of labour time, which cost $130,500.?

Required?

Calculate the labour planning and operational variances in as much detail as possible.?

?A planning variance compares what with what??

?A standard material cost is revised and the standard quantity of material required per unit is reduced in the?revised standard, compared with the original standard. At the same time, the standard rate per unit of?material is increased in the revised standard.?

?(a) The material price planning variance is ________________ (favourable/adverse)?

?(b) The material usage planning variance is ________________ (favourable/adverse)?

?Are variable production overhead variances based on hours paid or hours worked??

?Ideal standards are long-term targets.?

A

?True

B

?False?

?This objective test question contains a question type which will only appear in a computer-based exam, but this question provides valuable practice for all students whichever version?of the exam they are taking.?

While a drag and drop style question is impossible to fully replicate within a paper based?medium, some questions of this style have been included for completeness.?

A business is expanding rapidly and buying its material in a variety of countries in a variety?of currencies.? It has an exclusive supply delivery contract whereby the same logistics expert?makes all deliveries in to its warehouses on a cost plus basis.? It pays all delivery charges on?a per unit basis.?

Which of the following are valid explanations of an adverse material price variance?measured to include delivery costs as part of the cost per kg delivered??

Drag the correct items into the box below:

?? Exchange rate movements

?? Extra discounts agreed

?? Increased world-wide demand for the material

?? Extra supply of the material becoming available from new suppliers

?? World oil price rises

?? Increases in the dividends paid by the delivery business?

What are the possible advantages for the control function of an organisation of having a standard costing?system??